NamPower has invested more than N$21.8 billion in infrastructure over the past 30 years as it expands generation and transmission capacity to strengthen Namibia’s electricity supply.
NamPower managing director Kahenge Haulofu said the utility has maintained a stable financial position despite macroeconomic headwinds, enabling it to undertake projects ranging from small-scale developments to major power infrastructure.
Since 1999, NamPower’s profit after tax has increased from N$193 million to N$1.4 billion, while its asset base grew from N$3.8 billion to N$58 billion by 2025.
Cash flow generated from operations also increased from N$308 million in 1999 to N$1.9 billion in 2025. Haulofu said the company’s operating profit currently stands at N$1.3 billion, while its asset base has reached N$59 billion.
He said the utility’s financial discipline has strengthened its financial base and credibility with financial institutions and development funders, creating opportunities to secure financing for large-scale infrastructure projects.
NamPower’s existing generation fleet includes the 347 MW Ruacana hydroelectric power station, the 120 MW Van Eck coal-fired power station, the 76.5 MW Anixas power station and the 20 MW Omburu solar PV plant.
The utility has completed several generation projects in recent years, including the 54 MW Anixas II project in November 2024 and the 20 MW Khan Solar PV independent power producer project in May 2025.
The 20 MW Omburu PV project was completed in March 2022.
In the short term, NamPower has a 100 MW Rosh Pinah Solar PV project scheduled for the first quarter of 2027 and a 51 MW, one-hour Omburu battery energy storage system targeted for the third quarter of 2026.
Projects planned over the medium term include the 50 MW Cerim Wind project, a 44 MW Diaz Wind project, a 45 MW Lithops battery energy storage system, an 80 MW Omburu PV expansion, a 40 MW biomass project and a 120 MW solar PV independent power producer project.
NamPower’s longer-term strategic projects include the 440 MW Baynes Hydro Power Plant, with Namibia’s offtake targeted for 2032/33, a 475 MW gas-to-power project and a 300 MW Mega Wind project.
The utility said the development of mid-merit and baseload generation capacity remains necessary, with gas-to-power, hydropower and, over the longer term, nuclear energy among the options identified.
NamPower has set development targets of achieving 80% self-sufficiency in electricity supply and 70% renewable energy by 2030.
On the transmission side, the utility is undertaking several projects, including the 400kV Obib-Oranjemond interconnector with South Africa, the 400kV Auas-Kokerboom line, the Otjikoto-Masivi 220kV line and new Erongo and Khomas substations.
Other ongoing transmission projects include high-voltage direct-current earth electrodes and various grid-strengthening and substation upgrades in northern Namibia.
Strategic transmission infrastructure includes the Angola-Namibia interconnection, known as ANNA, and the 400kV Otjikoto-Omatando transmission line.