07
Sep
CHAMWE KAIRA NamPower, which plans to establish a wind power plant with a capacity of up to 40MW near Rosh Pinah, expects to shortlist applicants from the prequalification stage in October. The shortlisted firms will then be invited to bid for the Engineering, Procurement and Construction (EPC) of the plant in October. All things being equal, construction of the plant is expected to commence in June 2023, with an estimated duration of 18 months, NamPower Managing Director, Simson Kahenge Haulofu told Observer Money. “The time of completion of the project is thus anticipated to be in December 2024,” he says.…