CHAMWE KAIRA
Koryx Copper has valued its proposed Haib copper project in southern Namibia at US$2.5 billion (over N$42 billion) in after-tax net present value, with the project expected to produce an average of 130 000 tonnes of payable copper annually during its first 10 years of operation.
The company’s pre-feasibility study (PFS) estimates a 24-year mine life, upfront capital expenditure of US$2.06 billion (about N$37.1 billion) and an after-tax internal rate of return of 25%, based on a copper price assumption of US$5 per pound.
The project, located in the //Karas region near the South African border, is expected to produce copper alongside gold and molybdenum, with Koryx targeting the completion of a definitive feasibility study in 2027 and early construction works towards the end of that year.
The study estimates average annual payable copper production of 130 000 tonnes during the first decade, declining to 105 000 tonnes over the life of the mine.
Gross copper-equivalent production is projected at 145 000 tonnes annually during the first 10 years.
The project is expected to produce an average of 15 000 ounces of payable gold and 1.22 million pounds of payable molybdenum annually during its first decade.
The estimated after-tax net present value is US$2.5 billion, while the pre-tax value is US$4.2 billion. The after-tax internal rate of return is 24.9%, compared with 30.6% before tax.
The study estimates a post-tax payback period of 3.9 years. The project’s initial capital requirement includes US$133 million in contingency and US$152 million in capitalised pre-stripping costs.
Sustaining capital expenditure is estimated at US$639 million over the mine’s life.
Koryx estimates cash operating costs of US$1.72 per pound of payable copper during the first 10 years, increasing to US$2.19 per pound over the life of the mine.
All-in sustaining costs are projected at US$2.07 per pound initially and US$2.52 per pound over the full operation.
The proposed operation will use conventional open-pit mining. The processing plant is designed to handle 48 million tonnes of ore annually, using crushing, grinding and flotation.
The company plans to mine for approximately 15 years, while processing will continue for 24 years, including the treatment of stockpiled lower-grade material towards the end of the operation.
The study estimates total copper production of 2.61 million tonnes over the mine life, with copper recovery averaging 87.3% and increasing to 89.5% during the first 10 years.
Haib has a mineral resource containing approximately 3.57 million tonnes of copper in the indicated category and a further 781 000 tonnes in the inferred category.
The pre-feasibility study establishes probable mineral reserves of approximately 1.119 billion tonnes at an average copper grade of 0.27%, containing nearly 3 million tonnes of copper.
The reserve estimate also includes approximately 65 000 tonnes of molybdenum and 689 000 ounces of gold.
The proposed mine will require an estimated 1 650 gigawatt-hours of electricity annually, with peak demand of about 261 megavolt-amperes.
The power supply plan combines a 220-kilovolt connection to NamPower’s Harib substation with an approximately 417-megawatt-peak solar photovoltaic plant and 361 megawatt-hours of battery storage.
The renewable energy system is expected to supply about 45% of the mine’s electricity requirements over its life, with grid electricity providing the remainder.
Koryx has entered into a memorandum of agreement with NamPower and is advancing the design of the grid connection infrastructure.
It has also applied for approval to source up to 49.9% of its electricity requirements through the contestable market, subject to a power supply agreement with NamPower.
Water requirements are estimated at 20 million cubic metres annually, with the Orange River identified as the preferred source.
The proposed supply system will include an off-channel storage dam to manage seasonal flows and maintain supply during periods of low water availability.
The company has a memorandum of understanding with NamWater, while an infrastructure development agreement is under review.
The project also includes plans for a township near Noordoewercovering about 36.6 hectares, with 370 erven and capacity for approximately 2 000 residents. Koryx proposes constructing 543 housing units for its workforce.
Koryx expects the major permits, including the mining licence and environmental clearance certificate, to be secured by around mid-2027.
The company has submitted environmental clearance applications for the mine and water supply infrastructure, while applications for the proposed railway siding and bulk power infrastructure are expected to be submitted in mid-2027.
The mining licence application was submitted in September 2025, while the water abstraction licence application for 20 million cubic metres annually over 33 years was submitted in July 2026.
Koryx plans to undertake project financing and strategic options reviews alongside the study, with a construction decision expected to follow completion of the feasibility work.
The company is targeting early works towards the end of 2027, with construction expected to begin in the first quarter of 2028, subject to financing, permitting and approvals.
The financial projections are based on a long-term copper price of US$5 per pound, gold at US$3 500 an ounce and molybdenum at US$22 per pound.