Bannerman plans further exploration at Etango uranium project

CHAMWE KAIRA

Bannerman Energy plans further exploration at depth and across regional satellite targets, including Hyena, Onjamba, and Ompo.

The exploration programme forms part of the company’s broader development plans for its Etango Uranium Project in the Erongo Region, where full-scale construction is under way ahead of targeted first production in 2028.

Bannerman has also identified two potential expansion options beyond the initial development.

The Etango-16 expansion concept would double processing capacity to 16 million tonnes annually, increasing average production to 6.7 million pounds of U₃O₈ a year after the fifth year of operation.

The option carries an estimated incremental growth capital cost of US$367 million.

The second option, Etango-XT, would extend the mine life to 27 years at an annual processing capacity of eight million tonnes, with forecast total production of 95.2 million pounds of U₃O₈.

The November investor presentation was delivered by managing director and chief Executive Gavin Chamberlain at Canaccord Genuity’s Australia Mining Conference in Noosa, Queensland.

According to Bannerman, approximately 523 contractor personnel are currently working at the Etango site, located about 30 kilometres south-east of Swakopmund.

The project moved into full-scale construction following a positive Final Investment Decision (FID) in October 2026.

Construction progress includes the completion of approximately 99% of bulk earthworks, while the Phase 1 permanent water supply pipeline is about 90% complete.

The Etango-8 development is based on a two-year construction and commissioning schedule, with initial uranium production targeted for 2028.

Bannerman holds a 55% interest in the Etango joint venture, with China National Nuclear Corporation subsidiary CNNC Overseas Limited holding the remaining 45%.

The joint venture owns 95% of the project, while Namibia’s One Economy Foundation holds the remaining 5%.

The project has forecast pre-production capital expenditure of US$353 million and is fully funded without debt.

Bannerman reported that US$64 million had been spent by 30 September 2026, leaving approximately US$289 million in forecast capital expenditure.

The joint venture had US$295 million in cash at the end of September, sufficient to cover the remaining construction expenditure.

Bannerman also reported corporate cash holdings of A$174.6 million, equivalent to approximately US$122 million, excluding joint venture funds.

This is intended to cover its estimated US$60 million share of remaining working capital requirements.

Under the offtake agreement, CNNC Overseas Limited is entitled to 60% of the project’s life-of-mine uranium production at prevailing future market prices, without price floors or caps.

The remaining 40% is available for sale to third-party buyers.

The Etango-8 feasibility study provides for an initial 15-year mine life, with an annual processing capacity of eight million tonnes.

The project is forecast to produce 52.6 million pounds of uranium oxide (U₃O₈) over its mine life, averaging 3.5 million pounds annually at an all-in sustaining cost of US$39.10 per pound, based on a uranium price assumption of US$65 per pound.

At a long-term uranium price assumption of US$95 per pound, Bannerman forecasts post-tax net cash flow of US$1.951 billion.

The project has a JORC-compliant mineral resource of 206.8 million pounds of U₃O₈ and an ore reserve of 59.9 million pounds.